Update on 3/2/23:
Hallelujah! The paving of Cannondale Drive is complete!
Trash & recycling pick up will occur throughout the village on Friday, March 3 as normal.
Before the end of March Pave-Rite will return to apply thermoplastic striping at all STOP sign locations. There is minimal inconvenience for residents as it takes about 5 minutes after the striping is applied for traffic to resume as normal. There will be a walk-through inspection also with the road engineer. After that the road project will be complete.
Thank you all for your patience and to those who cooperated with the information and advice we provided.
Sharon Ziemba & Harry Treber, Fox Hollow Road Project
--------------------------------------------------------------------------------
High Level Task Schedule (See more detailed information below)
|
Task (Updated on 2/28/23) |
Duration (Days) |
Start Date |
Completion Date |
1 |
Mobilization of Project |
1 |
10/24/22 |
10/24/22 |
2 |
Pre-Construction Video |
2 |
10/25/22 |
10/26/22 |
3 |
Set-Up Staging Area |
1 |
10/27/22 |
10/27/22 |
4 |
De-Silt All Storm Drainage Pipes |
12 |
11/7/22 |
11/22/22 |
5 |
Set-Up Temporary Erosion Control |
2 |
11/22/22 |
11/23/22 |
6 |
Mill & Clean Litchfield, Torrington, & Havershall |
1 |
2/13/23 | 2/13/23 COMPLETED |
7 |
Asphalt Pave Litchfield, Torrington, & Havershall |
2 |
2/15/23 |
2/15/23 |
8 |
Mill & Clean Glynborne |
1 |
2/14/23 |
2/14/23 |
9 |
Asphalt Pave Glynborne |
2 |
2/15/23 |
2/16/23 |
10 |
Mill & Clean Cannondale |
2 |
2/27/23 |
2/28/23 |
11 |
Asphalt Pave Cannondale |
2 |
3/1/23 |
3/2/23 |
12 |
Apply Thermoplastic Striping at STOP signs |
2 |
||
13 |
Clean Areas Around Storm Drainage Area and Staging Area |
2 |
3/2/23 |
|
14 |
Final Inspection of Road Work |
1 |